MATC Revitalization Implementation Timeline

Remodel and Expansion Design Schedule

  • Programming: 1/17/25 – 3/07/25
  • Schematic Design/Site Plan: 3/10/25 – 4/18/25
  • Site Plan Review: 4/21/25 – 7/18/25
  • Design Development: 4/21/25 – 6/13/25
  • Construction Documents: 6/16/25 – 8/22/25
  • Permitting/Bidding/Contracts: 8/25/25 – 12/31/25
  • Construction: 01/05/26 – 04/02/27